Lehi 2300 West Road Improvements from 2150 North to Main Street

Lehi City Logo.png

Lehi 2300 West Road Improvements from 2150 North to Main Street

OVERVIEW

The City of Lehi has hired Kenny Seng Construction to improve 2300 West from Main Street to 2150 North.

These improvements include:
* Street changes from three lanes to five lanes.
* Connect the Waste Ditch Trail between 2375 and 2300 West (The trail will cross 2300 West at a new pedestrian traffic signal)
* Install curb, gutter and sidewalk where it does not exist now.
* Enhance ADA accessibility at intersections.
* Install a pedestrian activated HAWK (high-intensity activated crosswalk beacon) at the southeast corner of North Point Elementary School on 2300 West.

 

This is a multi year project, for the year 2024, the contractor will start working along the northern part of the project.

SCHEDULE

Work begins: June 11, 2024

Anticipated Project End: Fall of 2025

Workdays: Monday - Friday, with some occasional work on Saturdays.

Work hours: 7:00 a.m. to 6:30 p.m., with occasional night work.

Map for flyer entire project dh edits.jpg

EXPECTED IMPACTS

Traffic lanes will shift within the active project area. Occasionally property accesses and side streets will be temporarily closed while crews are working directly in front of them. Expect heavy construction equipment that will produce noise, dust and vibration from operations. Night work may include noise from jack hammering, audible backup warning, metal scraping on pavement and other construction noises.  Through the active construction zone expect delays and congestion, alternate routes are encouraged to avoid unnecessary delays.  During construction, some ADA ramps, curb, gutter and sidewalk sections may be removed and replaced as quickly as possible.  During these events, please look for signage giving direction and alternate routes.

SAFETY

During construction motorists, pedestrians, and cyclists please be cautious in the active project area. Please reduce speed when traveling through construction zone. Give workers, trucks or equipment extra room. Please obey all posted speed limits and follow all construction signage.

 

Note: Schedules are subject to change due to weather, material availability and other unforeseen conditions.

STAY INFORMED

We encourage you to sign up for the weekly email update that will provide information about where the contractor is working and the expected impacts for the coming week. Send an email to: lehi2300west@gmail.com and write “Updates” in the subject line.